권호기사보기
| 기사명 | 저자명 | 페이지 | 원문 | 기사목차 |
|---|
결과 내 검색
동의어 포함
Title page 1
Contents 3
Highlights 2
Letter 7
Background 10
Acquisition Process for NNSA Major Projects 10
NNSA Cost and Schedule Commitments 13
Design and Technology Maturity 15
Nuclear Security Enterprise Sites 16
NNSA Major Projects Reviewed in GAO's Assessment 17
NNSA Major Projects Excluded from GAO's Assessment 19
Recent GAO Work on Selected NNSA Projects 20
NNSA's Portfolio of Major Projects in the Execution Phase Continues to Face Cost Overruns and Schedule Delays 22
Most Projects in Definition Phase Are Implementing Significant Design Changes, and Those with Critical Technologies Have Reached Maturity Milestones 27
Projects Are at Different Stages of Design Maturity, and Most Are Implementing Design Changes or Experiencing Design Challenges 27
Projects in the Definition Phase with Critical Technologies Have Reached Maturity Milestones 32
Agency Comments 32
Appendix I: Individual Project Summaries 34
Appendix II: Objectives, Scope, and Methodology 80
Appendix III: Estimated Costs and Schedules for the National Nuclear Security Administration's Projects Assessed by GAO 83
Appendix IV: Estimated Costs and Schedules for Major Projects in the Initiation Phase 86
Appendix V: Estimated Costs and Schedules for the Major Projects Managed by the Office of Naval Reactors 87
Appendix VI: Design Costs and Schedules for the National Nuclear Security Administration's Projects Assessed by GAO 88
Appendix VII: Technology Readiness Levels 91
Appendix VIII: GAO Contact and Staff Acknowledgments 93
Appendix IX: Additional Source Information for Images and Figures 94
Related GAO Products 95
Tables 4
Table 1. NNSA's 28 Major Projects Assessed by GAO, by Phase and Site, as of June 2025 18
Table 2. Cost and Schedule Performance of 16 NNSA Major Projects in the Execution Phase, as of June 2025 23
Table 3. Design Review Status for NNSA's 12 Major Projects in the Definition Phase, as of June 2025 28
Table 4. NNSA Major Projects in the Definition Phase Implementing Design Changes or Facing Design Challenges, as of June 2025 29
Table 5. Four NNSA Major Projects in the Definition Phase Have Identified Critical Technologies, as of June 2025 32
Table 6. Preliminary Cost and Schedule Estimates for NNSA's 12 Major Projects in the Definition Phase, as of June 2025 83
Table 7. Cost and Schedule Estimates for NNSA's 16 Major Projects in the Execution Phase, as of June 2025 84
Table 8. Initial Cost and Schedule Estimates for NNSA's Nine Major Projects in the Initiation Phase, as of June 2025 86
Table 9. Preliminary Cost and Schedule Estimates for the National Nuclear Security Administration Office of Naval Reactor's Major Projects... 87
Table 10. Cost and Schedule Estimates for the National Nuclear Security Administration Office of Naval Reactor's Major Projects... 87
Table 11. Estimates of Time to Complete Design Activities and Associated Costs for NNSA's 12 Major Projects in the Definition Phase,... 88
Table 12. Time to Complete Design Activities and Associated Costs for NNSA's 16 Major Projects in the Execution Phase, as of June 2025 89
Table 13. Department of Energy Technology Readiness Levels (TRL) 91
Figures 5
Figure 1. GAO Presentation of Acquisition Phases for NNSA Major Projects 12
Figure 2. Sites in the Nuclear Security Enterprise 17
Figure 3. Cumulative Cost and Schedule Overruns for NNSA's Portfolio of Major Projects in Execution Phase, 2023 to 2025 23
Figure 4. Illustration of a Sample Project Summary 35
*표시는 필수 입력사항입니다.
| 전화번호 |
|---|
| 기사명 | 저자명 | 페이지 | 원문 | 기사목차 |
|---|
| 번호 | 발행일자 | 권호명 | 제본정보 | 자료실 | 원문 | 신청 페이지 |
|---|
도서위치안내: / 서가번호:
우편복사 목록담기를 완료하였습니다.
*표시는 필수 입력사항입니다.
저장 되었습니다.