Title page 1
Contents 1
Key Takeaways 1
Background 2
What legal framework governs EM's Moab Cleanup Project? 2
How much has DOE spent, and what work has been completed? 4
What are the remaining costs and work? 5
What does EM plan to do with the Moab Mill Site once cleanup is complete? 6
How may the Moab Mill Site be used in the future, and what are the views of stakeholders on these uses? 7
Has EM followed leading practices while engaging with selected stakeholders about the future use of the Moab Mill Site? 7
How has EM coordinated with LM regarding the completion of the Moab Cleanup Project? 8
Agency Comments 9
How GAO Did This Study 9
List of Committees 10
GAO Contact Information 10
Figure 1. Moab Mill Site and Surrounding Area 2
Figure 2. Overview of Federal Cleanup and Control Standards for the Department of Energy's Moab Mill Site and Crescent Junction Disposal Site 3
Figure 3. Department of Energy Spending on Moab Cleanup Project Through Fiscal Year 2025 4
Figure 4. Department of Energy Cleanup Activities at the Moab Mill Site and Crescent Junction Disposal Site 6